This is a notice to update residents of an out-of-hours delivery of machinery to Church Street Site A scheduled for Monday 27 July.
Site A will see 430 new homes built. 215 of these new homes will be affordable, with 70% of these affordable homes let at Social Rent. Site A will also be home to a new library and new spaces for shops.
- The delivery of two piling rig machines to site is scheduled between 5:00-6:00am, with the aim to be off site before 7:00am.
- Due to its large size, the delivery needs to take place outside normal working hours for safety reasons. This has been agreed with Westminster City Council via approved section 61 notice
- The delivery of these machines will enable the piling phase of the construction works to continue. Piling is the process of driving or drilling massive poles (called "piles") deep into the earth to act as the hidden legs of a building. It is used when the top layer of ground is too soft or weak to hold the heavy weight of a structure
Please be assured that noise will be kept to a minimum, with specific positioning of the delivery trailer ensuring minimal disruption. There will be no need for any other movement until working hours commence at 8:00am.
If you have any queries, please contact Church Street Site A’s Project Director, Sean Kelly, at [email protected]
Thank you for your cooperation.