Thames Water works from May - June 2026

Thames water will be carrying out works which will effect surrounding streets around Church Street.
The works are as follows:

First phase works will commence on the 18th May from the corner of Salisbury Street and Broadley Street to the corner of Mulready Street. Works have already begun on Mulready Street and will remain open to traffic. This phase will take 3 weeks and complete on the 8th June.

Second phase will start immediately after and run from the corner of Salisbury Street and Church Street to same corner of Mulready as above. This phase will take 2 weeks and complete 23rd June.

If you have any questions or concerns, please contact Thames Water 24 hour emergency number on 0800 316 9800 or just speak to one of the site mangers.